Column की Shuttering कब निकाले | What is The Minimum De - Shuttering Duration For Column?

Column की Shuttering कब निकाले | What is The Minimum De - Shuttering Duration For Column?

Positive Builder

2 года назад

1,433 Просмотров

De – Shuttering Period as per IS 456 – 2000
De shuttering period relates to the maturity of concrete and depends on the ambient temperature.

Forms shall not struck until the concrete has reached strength at least twice the stress of which the concrete may be subjected at the time of removal of form work.
Form Summers Winters (Temp Less then18° C)
Walls, columns and vertical faces of structural members 16 hrs. 24 hrs.
Removal of props under slab Spanning up to 4.5 m 7 days 14 days
Removal of props under beams and arches spanning up to 6 m 14 days 28 days
Soffit form work to slabs 3 days (props to be refixed after removal)
Soffit to beams props 7 days props to refixed after removal.

#Shuttering #Formwork #Time

Column की Shuttering कब निकाले | What is The Minimum De - Shuttering Duration For Column?

CIVIL ENGINEER
AVINASH SHARMA

POSITIVE BUILDER
https://www.youtube.com/channel/UCFjH8uA8Z7SCnzzX-kwCl9w

Тэги:

#Column_की_Shuttering_कब_निकाले_|_What_is_The_Minimum_De_-_Shuttering_Duration_For_Column? #What_is_The_Minimum_De_-_Shuttering_Duration_For_Column? #de_shuttering_minimum_period #de_shuttering_of_beam #de_shuttering_of_slab #deshuttering_as_per_is_456 #deshuttering_of_column #deshuttering_of_formwork #deshuttering_period #deshuttering_period_as_per_is_456 #deshuttering_period_of_slab #deshuttering_time #deshuttering_time_of_formwork #stripping_period_as_per_456