Project crashing full example (part 1/2)

Project crashing full example (part 1/2)

Engineer4Free

9 лет назад

305,329 Просмотров

Ссылки и html тэги не поддерживаются


Комментарии:

@sojanmathew6764
@sojanmathew6764 - 19.07.2023 20:10

Hello! I have problem same related to this. How can I contact you for this ? Thanks

Ответить
@joeytadayo6941
@joeytadayo6941 - 25.06.2023 16:25

I thought you first calculate the slope to determine which is the lowest amount to crash

Ответить
@andrewandretti5339
@andrewandretti5339 - 15.06.2023 12:20

You're the worst teacher, mate

Ответить
@a_potat
@a_potat - 05.04.2023 16:29

quick question. why not have the start as 1? since the first day is one , then start day for the next activity to be end date of first act+1?

Ответить
@samuelutsu7263
@samuelutsu7263 - 24.01.2023 23:10

awesome and very detailed. thank you

Ответить
@sylvamadu3721
@sylvamadu3721 - 05.12.2022 01:00

super useful dude!!!! Thanks man

Ответить
@asi1968
@asi1968 - 16.11.2022 01:19

C has a total float of 1
Or I’m getting this wrong ?

Ответить
@clemencejacob4159
@clemencejacob4159 - 12.10.2022 08:02

quite helpful. It requires practice oftenly

Ответить
@mohammedabdalhadi1798
@mohammedabdalhadi1798 - 11.08.2022 17:23

In Run 2 the project cost cannot be reduced as long as the duration is reduced

Ответить
@Hgb9999
@Hgb9999 - 03.06.2022 20:31

can i knw book where u got question?

Ответить
@Wellsy-qr8pb
@Wellsy-qr8pb - 21.04.2022 18:26

Litterally creats wholemside table and jsut skips right by the explanatnion thanks for nothing jerk

Ответить
@shibadaddy8639
@shibadaddy8639 - 14.04.2022 15:11

you are the professorrrr

Ответить
@abdullahtahir3693
@abdullahtahir3693 - 25.12.2021 16:59

In run 2 there will be total float of 1 at C but you write it in B row correct it sir 👍

Ответить
@jasoncysiu
@jasoncysiu - 27.10.2021 04:42

You saved ooour life in 9 minutes -- something that the DOCTOR (or so called PhD) cannot even do! Legendary!

Ответить
@baijumehta8495
@baijumehta8495 - 27.03.2021 10:40

Thanks for a wonderful and very clear explanation. Would like to know which tool did you use for drawing the Network Diagram.

Ответить
@TheAbdallahalmassri
@TheAbdallahalmassri - 06.12.2020 07:39

Amazing succinct explanation. thank you

Ответить
@mushayatikamal7890
@mushayatikamal7890 - 21.11.2020 04:25

Thank you for this link Dr.

Ответить
@mazrimamat9899
@mazrimamat9899 - 13.11.2020 15:49

Useful information about project crashing.Thank you

Ответить
@fatimahhafizahmamat4340
@fatimahhafizahmamat4340 - 01.11.2020 17:48

Thank you

Ответить
@kavilenraaj3084
@kavilenraaj3084 - 30.09.2020 12:46

Can I know why you didn't choose activity c which is 400 is cheap to crash?

Ответить
@anishsule3283
@anishsule3283 - 26.09.2020 20:58

Good stuff..God Blessed

Ответить
@alaamohamed-vt9xq
@alaamohamed-vt9xq - 23.09.2020 19:26

in the first crash process when crashing the duration from 18 to 17, should we also remove the cost of one day from E activity so the new total cost would be 16,900 instead of 18,800 and do the same for the other crashes

Ответить
@divinelymoi
@divinelymoi - 03.07.2020 08:29

How do you calculate the crash duration?

Ответить
@fahimqasimi2481
@fahimqasimi2481 - 27.04.2020 00:04

Great job. Thank you!

Ответить
@stellathai4999
@stellathai4999 - 19.04.2020 04:34

how can you figure the total float?

Ответить
@ahmadammar9516
@ahmadammar9516 - 05.04.2020 20:44

Nicely explained....but seems a typo here: how come table on the top shows 'E,F' as predecessors to 'E' ?? I believe these are 'C,D'

Ответить
@peterlisena3509
@peterlisena3509 - 20.03.2020 04:39

How would you find the minimum expected time that a project can be completed?

Ответить
@knifewars5131
@knifewars5131 - 01.02.2020 19:39

Very useful. I didn't know wich activity of the critical path crash first.

Ответить
@pratiklohar4566
@pratiklohar4566 - 04.12.2019 11:59

Undoubtedly Best Explanation on Crashing Ever ...!! U made one small mistake while writing TF in run-2.

Ответить
@anitap.4472
@anitap.4472 - 28.11.2019 04:30

How would you calculate the Net Profit?

Ответить
@mariaerickanicolas
@mariaerickanicolas - 19.11.2019 14:56

Thank youuu!!

Ответить
@allysamariejipus4247
@allysamariejipus4247 - 20.10.2019 18:25

Hi. Isn’t the project cost on run 1 supposed to to be 18,400? ..

Ответить
@henryanda425
@henryanda425 - 21.03.2019 14:35

Nice video very helpful....but the predecessor for activity E is C & D not E & F please correct that.

Ответить
@cartoonchannel1480
@cartoonchannel1480 - 26.07.2018 07:34

How you are calculating the additional cost

Ответить
@nicholeh1280
@nicholeh1280 - 13.07.2018 08:30

So very helpful! This and part two. I would not have gotten this right from just reading the text book.

Ответить
@dankd1069
@dankd1069 - 15.04.2018 22:21

instead of overhead cost what if it said company will get x amount of reward per day if completed early? how would we amount that

Ответить
@sibusisombhele3880
@sibusisombhele3880 - 19.03.2018 05:31

Thank so much you are such a blessing, God bless you

Ответить
@sunilchanda1212
@sunilchanda1212 - 26.02.2018 11:11

can you tell me what actually is overhead cost is it labor charge and activity cost means material cost??

Ответить
@nada2excoo
@nada2excoo - 06.02.2018 14:04

Thanks a lot for your videos. Can you tell me how you calculate crash duration?

Ответить
@user-ui6bd6zj5u
@user-ui6bd6zj5u - 25.11.2017 20:30

I think you made a mistake in TF of the second round, am I right?

Ответить
@phanminhquan1285
@phanminhquan1285 - 09.11.2017 14:15

Appreaciated this a lot. Thank you

Ответить
@user-mc9rr7zt3l
@user-mc9rr7zt3l - 17.07.2017 16:57

hello! thanks for the videos. on run 2 Tf=1 should be on activity C or am I wrong?

Ответить
@brahimelboudani601
@brahimelboudani601 - 15.01.2017 04:13

I just want to get this right. You said we should start crashing the activity with the lowest cost on the critical path. B= 400 and E=500. Could you please explain why you crashed E first? I a bit confused there

Ответить
@SlimJimBigWin
@SlimJimBigWin - 15.06.2016 01:12

Thanks for the video, there is a typo in the predecessor column since the predecessor of E is also E and there is an F while there is no F as an activity.

Ответить